Sulfur Recovery Loading Rack

CHEVRON REFINERY

Project Value: $5 Million

Scope


Civil construction of eight new concrete foundations and one loading rack foundation, to facilitate erection of structural steel and installation of mechanical piping to support the new loading rack and its necessary pumps, structures and amenities.

  • Project Specialties
  • Pile Driving
  • Excavation
  • Grading
  • Underground
  • Electrical
  • Masonry
  • Paving
  • Structural Steel
  • Mechanical Piping

Challenge

Maintaining unimpeded access to the current loading rack while completing civil/structural, mechanical and piping installation for the replacement sulfur truck loading rack to increase the truck loading capacity and improve safety.

Solution


By coordinating with operations and traffic plans during the 12+ month project to off-haul sulfur at the existing loading rack, we assisted in constructing the new loading rack without impeding necessary truck traffic.

Project Success


The new rack and its necessary foundations were safely completed.