Fresno P&DC Asphalt Replacement

Fresno P&DC Asphalt Replacement

UNITED STATES POSTAL SERVICE

Project Value: $500,000

Scope


Fresno P&DC operations and employee lot asphalt replacement included the removal and replacement of 170,000 square feet of existing asphalt concrete.

  • Critical scheduling
  • Excavation
  • Asphalt Paving
  • Striping/Pavement Markings

Challenge

Project needed to be performed in an operational facility.

Solution


Management and leadership came up with solution with the postmaster to allow for continuous operation of the postal facility. Coordination included phasing and swing shift work.

Project Success


We completed the project with no interruption to facility operations.


Sulfur Recovery Loading Rack

Sulfur Recovery Loading Rack

CHEVRON REFINERY

Project Value: $5 Million

Scope


Civil construction of eight new concrete foundations and one loading rack foundation, to facilitate erection of structural steel and installation of mechanical piping to support the new loading rack and its necessary pumps, structures and amenities.

  • Project Specialties
  • Pile Driving
  • Excavation
  • Grading
  • Underground
  • Electrical
  • Masonry
  • Paving
  • Structural Steel
  • Mechanical Piping

Challenge

Maintaining unimpeded access to the current loading rack while completing civil/structural, mechanical and piping installation for the replacement sulfur truck loading rack to increase the truck loading capacity and improve safety.

Solution


By coordinating with operations and traffic plans during the 12+ month project to off-haul sulfur at the existing loading rack, we assisted in constructing the new loading rack without impeding necessary truck traffic.

Project Success


The new rack and its necessary foundations were safely completed.


Pipe Support Replacement

Pipe Support Replacement Project

Pipe Support Replacement Project

CHEVRON REFINERY

Project Value: $2 Million

Scope


Civil construction to widen and increase the mass of 57 existing concrete foundations and upgrade the baseplates and structural steel on 40 bents.

  • Project Specialties
  • Excavation
  • Underground
  • Masonry
  • Structural Steel

Challenge

Completing seismic repairs and upgrades to the existing Standard Road Pipe Rack that was built in the early 1970s and experienced severe damage due to corrosion at multiple beams, columns, vertical bracing and anchor bolts – all in accordance with the 2013 California Accidental Release Prevention Program Seismic Assessments and the 2016 California Building Code. We also performed voluntary modifications to the lateral-force resisting system.

Solution


Faced with difficult excavations that required abnormal shoring installation and complex layout, we noticed an unexpected large boulder that presented a hazard to perform the necessary excavation began. We helped redesign the structural upgrades and eliminate the hazard of the boulder, keeping the field crews safe during the seismic retrofit.

Project Success


Provided constructibility and value engineering for the retrofits and to the soils engineer.


Bay View Site Access Improvement

Bay View Site Access Improvement

LAWRENCE BERKELEY NATIONAL LABORATORY

Project Value: $5 Million

Scope


Demolish existing reinforced concrete structure to provide the real estate for new building construction, relocate existing compressed air line, install new fire and domestic water lines, install soldier pile with several rows of tie-backs, install new reinforced concrete retaining walls and new stair structures.

  • Demolition
  • Soil Disposal
  • Site Restoration
  • Relocation of Underground Utilities
  • Grading
  • Paving
  • New Retaining Wall Construction
  • Underground

Challenge

The underground compressed air line was in a challenging location and a Bay Area Quality Management District Permit and Soil Disposal Profile was not covered in the design drawings.

Solution


We prioritized the project activities and stockpiled the soil for testing to accommodate and achieve the project schedule.

Project Success


We prevented a more than six month delay to the project schedule and new building construction started as planned.