CVX/EBMUD RO Plant

CVX/EBMUD RO Plant

CHEVRON REFINERY

Project Value: $4 Million

Scope


Expand plant to receive and process EBMUD reverse osmosis water.

Challenge

We needed to install 3,500LF of 316 stainless steel pipe from EBMUD to Chevron’s treatment facility. This work included site excavation and grading, concrete foundations, installation of pumps and filter, pipe racks and critical tie-ins during the plant shutdown.

Solution


Before construction began, we noticed the project was designed with a standard sewer system. We helped redesign and construct a sewer system that met process refinery requirements.

Project Success


We completed the project on time, under budget and 100% injury-free. Plants were able to receive, treat and use most all of the Richmond plant outfall waste, which reduced or eliminated discharge to the San Francisco bay.


Sulfur Recovery Loading Rack

Sulfur Recovery Loading Rack

CHEVRON REFINERY

Project Value: $5 Million

Scope


Civil construction of eight new concrete foundations and one loading rack foundation, to facilitate erection of structural steel and installation of mechanical piping to support the new loading rack and its necessary pumps, structures and amenities.

  • Project Specialties
  • Pile Driving
  • Excavation
  • Grading
  • Underground
  • Electrical
  • Masonry
  • Paving
  • Structural Steel
  • Mechanical Piping

Challenge

Maintaining unimpeded access to the current loading rack while completing civil/structural, mechanical and piping installation for the replacement sulfur truck loading rack to increase the truck loading capacity and improve safety.

Solution


By coordinating with operations and traffic plans during the 12+ month project to off-haul sulfur at the existing loading rack, we assisted in constructing the new loading rack without impeding necessary truck traffic.

Project Success


The new rack and its necessary foundations were safely completed.


Pipe Support Replacement

Pipe Support Replacement Project

Pipe Support Replacement Project

CHEVRON REFINERY

Project Value: $2 Million

Scope


Civil construction to widen and increase the mass of 57 existing concrete foundations and upgrade the baseplates and structural steel on 40 bents.

  • Project Specialties
  • Excavation
  • Underground
  • Masonry
  • Structural Steel

Challenge

Completing seismic repairs and upgrades to the existing Standard Road Pipe Rack that was built in the early 1970s and experienced severe damage due to corrosion at multiple beams, columns, vertical bracing and anchor bolts – all in accordance with the 2013 California Accidental Release Prevention Program Seismic Assessments and the 2016 California Building Code. We also performed voluntary modifications to the lateral-force resisting system.

Solution


Faced with difficult excavations that required abnormal shoring installation and complex layout, we noticed an unexpected large boulder that presented a hazard to perform the necessary excavation began. We helped redesign the structural upgrades and eliminate the hazard of the boulder, keeping the field crews safe during the seismic retrofit.

Project Success


Provided constructibility and value engineering for the retrofits and to the soils engineer.


Old Town Utility Corridor (12kV)

Old Town Utility Corridor (12kV)

LAWRENCE BERKELEY NATIONAL LABORATORY

Project Value: $5 Million

Scope


Install new 12 kV ductbank and utility corridor for future development. Relocate utilities including main gas line and main compressed air line. Reroute and install new storm drain line.

  • Demolition
  • New Retaining Wall Construction
  • Underground Utilities
  • Site Restoration
  • Grading
  • Paving
  • Masonry
  • Mechanical Piping

Challenge

Existing underground utilities locations and the existing main gas line were not shown in design drawings. Compressed air line cut-over and relocation had not been studied and designed based on the limitations of research buildings and other laboratories during the design process. Most of the underground utilities were an unforeseen obstruction during the construction. The project next to the Advance Light Source building could not disturb research by producing any vibration in the vicinity.

Solution


We redesigned the main gas line and compressed air line relocation to comply with the research and laboratory operations. Because of the Advance Light Source vibration restriction, we completed excavation with nomadic hammer and demolition of the reinforced concrete structure with a concrete processor as a precaution when moving the heavy equipment. We also coordinated with the client to use a jackhammer for demolition/excavation, jumper jack and vibratory roller for backfilling and paving during the ALS maintenance shutdown window.

Project Success


Provided safe and efficient service to a facility that has very unique needs so its research could continue uninterrupted.